How do you calculate concrete for a Sonotube (tube form)?

Short answer

Use the cylinder formula: π × radius² × depth ÷ 27. A 10-inch diameter tube, 4 feet deep: 3.1416 × 0.417² × 4 ÷ 27 = 0.081 yards — about 6 bags of 60-lb mix. Buy one extra bag per tube; tubes are never perfectly round once backfilled.

Bags per 4-foot tube by diameter

Tube diameterVolume (4 ft deep)60-lb bags
8 in1.40 ft³4 bags
10 in2.18 ft³6 bags
12 in3.14 ft³7 bags
16 in5.59 ft³13 bags

How to read this table

Context

Tube diameter follows the load: 8-inch for deck posts and mailboxes, 10–12 inch for deck beams and small structures, 16-inch+ for porch roofs and heavy loads — but the building department's frost depth and footing-size table is the authority. Set the tube 6 inches into a gravel base, brace it plumb before pouring, and rod the concrete (or tap the tube) as you fill to release air pockets that weaken the pier.

What moves this number

Regional pricing

Ready-mix, bag, and labor prices vary 30–50% between US metros. Sun Belt markets with many plants run well below Northeast and remote-area pricing.

Waste and site conditions

Uneven subgrade, spillage, and form bowing consume 5–15% extra material. Orders placed at exact volume routinely come up short mid-pour.

Local code requirements

Frost depth, footing dimensions, and reinforcement rules are set by county. The same project can require twice the concrete in a northern climate versus a southern one.

Methodology

Cylinder volume at nominal tube diameters; bag counts at the published 0.45 ft³ yield for 60-lb mix, rounded up. Sizing guidance follows IRC R403 footing tables; local code governs.

Assumptions and caveats

Frequently asked questions

How do you calculate concrete for a Sonotube (tube form)?

Use the cylinder formula: π × radius² × depth ÷ 27. A 10-inch diameter tube, 4 feet deep: 3.1416 × 0.417² × 4 ÷ 27 = 0.081 yards — about 6 bags of 60-lb mix. Buy one extra bag per tube; tubes are never perfectly round once backfilled.

Which option pays the most in the bags per 4-foot tube by diameter table?

16 in, at 5.59 ft³ (13 bags). That row represents the strongest case in this dataset, so use it as an upper bound rather than an expectation.

What is a realistic low-end figure?

8 in at 1.40 ft³ (4 bags). Plan your costs so the low end still works, then treat anything above it as upside.

Why do the numbers vary so much?

The spread between the highest and lowest row is about 4.0×. Regional pricing and waste and site conditions explain most of that gap — see the drivers section above for the full list.

Where do these numbers come from?

Cylinder volume at nominal tube diameters; bag counts at the published 0.45 ft³ yield for 60-lb mix, rounded up. Sizing guidance follows IRC R403 footing tables; local code governs.

How can I estimate my own number instead of using a benchmark?

Use the Concrete Cost Calculator on RevenueLab — it takes your own inputs and returns a figure specific to your setup, which is always more accurate than a published range.

Model your own numbers

Related reading

More answers in this category

Looking for a calculator?

Search every free tool on RevenueLab — or describe your problem and Rex will pick one.

Last updated 2026-10-01.