General Conditions Percentage Calculator

Turn jobsite overhead staffing and rentals into a % of hard cost.

Revenue Rex peeking

Rex says

Money math without the spreadsheet headache. Plug in your numbers and I'll show you exactly where the dollars land.

Try a scenario

Click to load — tweak from there.

Inputs

Result

GCs as % of hard cost

8.18%

GC lump sum

$180,000

Total cost (hard + GC)

$2,380,000

GC burn rate per day

$592

Revenue Rex peeking

Psst — share this and help Rex grow

One click, a permanent link with your numbers baked in.

More financial

How to use this

  1. 1Enter monthly gc cost ($).
  2. 2Enter project duration (months).
  3. 3Enter hard construction cost ($).
  4. 4Read your gcs as % of hard cost on the right — it updates as you type.
  5. 5Hit Share to keep the scenario or send it to someone.

About this calculator

General conditions (GCs) are the non-trade costs of running the jobsite: superintendent salary, site trailer, temp power and water, portable toilets, dumpsters, safety supplies, small tools, and project engineer time. Estimators typically build GCs as a lump sum from a duration-based staffing plan, then check the result against a percentage of the hard construction cost to sanity-check the number against project size. Commercial GC ranges run 5-12% of hard cost for a typical 6-18 month job; small renovations run higher (10-15%) because fixed costs don't scale down, and large multi-year jobs run lower (3-6%) because staffing spreads over more volume. This tool takes your monthly GC burn rate and project duration, computes the lump sum, and expresses it as a percentage of hard cost so you can compare it against industry benchmarks before you finalize the number in your bid.

FormulaGC lump sum = Monthly GC cost × Duration (months). GC % = GC lump sum ÷ Hard cost × 100.

Worked example

Using the values the calculator loads with:

Inputs

  • Monthly GC cost: 18000 $
  • Project duration: 10 months
  • Hard construction cost: 2200000 $

Results

  • GCs as % of hard cost: 8.18%
  • GC lump sum: $180,000.00
  • Total cost (hard + GC): $2,380,000.00
  • GC burn rate per day: $592.11

What each field means

Inputs

Monthly GC cost ($)
The monthly gc cost used in the calculation, measured in $. Starts at 18000 $ so you have a working example on load.
Project duration (months)
The project duration used in the calculation, measured in months. Starts at 10 months so you have a working example on load.
Hard construction cost ($)
The hard construction cost used in the calculation, measured in $. Starts at 2200000 $ so you have a working example on load.

Results

GCs as % of hard cost
Returned as a percentage and shown as the headline result. It recalculates instantly whenever you change an input, so you can compare scenarios without reloading.
GC lump sum
Returned as a money amount in US dollars. It recalculates instantly whenever you change an input, so you can compare scenarios without reloading.
Total cost (hard + GC)
Returned as a money amount in US dollars. It recalculates instantly whenever you change an input, so you can compare scenarios without reloading.
GC burn rate per day
Returned as a money amount in US dollars. It recalculates instantly whenever you change an input, so you can compare scenarios without reloading.

FAQ

What counts as a general condition versus a direct cost?

GCs are costs that exist because the job is happening, not because of a specific scope item: supervision, temp facilities, safety, project controls, cleanup. If a cost is tied to installing a specific material (rebar, drywall, conduit) it's a direct/hard cost even if it's on the same invoice as a GC item. Getting this split wrong understates your GC line and makes future bids look artificially cheap.

Why does GC percentage drop on larger jobs?

Superintendent and PM salaries are largely fixed regardless of project size — one super can run a $2M job or, with tighter oversight, a $6M job. As hard cost scales up faster than staffing, the percentage falls. That's why applying a flat 8% GC rule to both a $500K tenant improvement and a $20M building will misprice one of them badly; build from staffing plans, not a blanket percentage.

How do I handle GCs on a fast-track or accelerated schedule?

Compressing duration doesn't proportionally cut GC cost because you often need the same or more supervision packed into fewer months, plus overtime premiums. Model accelerated schedules with a duration multiplier of 1.15-1.3x on monthly burn rate rather than just shrinking the months, or you'll underbid the acceleration.

Should bonds and insurance be inside or outside the GC number?

Most contractors carry builder's risk, general liability, and bond premiums as separate line items below GCs, not folded in, because they're calculated off total contract value rather than duration. Keeping them separate also makes it easier to re-price GCs alone when a schedule slips without recalculating insurance.

Accuracy and limitations

  • Results are estimates before tax, fees, and inflation unless an input explicitly covers them.
  • Rates are treated as fixed for the whole period — variable-rate products will drift from this projection.
  • This is educational maths, not financial advice. Check anything contractual with the lender or your accountant.

Related tools

Cite this calculator

Writing about this topic? Grab a citation — every link helps keep these tools free.

APA
RevenueLab. (2026). General Conditions Percentage Calculator. Retrieved from https://www.revenuelab.fyi/toolbox/general-conditions-percentage
HTML
<p>Source: <a href="https://www.revenuelab.fyi/toolbox/general-conditions-percentage" target="_blank" rel="noopener">General Conditions Percentage Calculator — RevenueLab</a> (2026).</p>
Markdown
Source: [General Conditions Percentage Calculator — RevenueLab](https://www.revenuelab.fyi/toolbox/general-conditions-percentage) (2026).
Advertisement