  "name": "How many bags of concrete make a cubic yard?",
  "description": "One cubic yard takes 90 forty-pound bags, 60 sixty-pound bags, or 45 eighty-pound bags. An 80-lb bag yields about 0.60 cubic feet, and a yard is 27 cubic feet: 27 ÷ 0.60 = 45 bags.",
  "url": "https://www.revenuelab.fyi/answers/how-many-bags-of-concrete-per-yard",
  "dateModified": "2026-10-01",
  "creator": {
    "@type": "Organization",
    "name": "RevenueLab",
    "url": "https://www.revenuelab.fyi"
  },
  "license": "https://creativecommons.org/licenses/by/4.0/",
  "keywords": [
    "Concrete Cost Calculator",
    "Concrete Slab Cost Calculator",
    "Concrete Slab Material Calculator"
  ],
  "distribution": {
    "@type": "DataDownload",
    "contentUrl": "https://www.revenuelab.fyi/api/public/page.json?path=answers%2Fhow-many-bags-of-concrete-per-yard",
    "encodingFormat": "application/json"
  },
  "json": {
    "type": "answer",
    "question": "How many bags of concrete make a cubic yard?",
    "shortAnswer": "One cubic yard takes 90 forty-pound bags, 60 sixty-pound bags, or 45 eighty-pound bags. An 80-lb bag yields about 0.60 cubic feet, and a yard is 27 cubic feet: 27 ÷ 0.60 = 45 bags.",
    "tableTitle": "Bags per cubic yard by bag size",
    "columns": [
      "Bag size",
      "Yield per bag",
      "Bags per yard"
    ],
    "rows": [
      {
        "label": "40 lb",
        "value": "0.30 ft³",
        "note": "90 bags"
      },
      {
        "label": "50 lb",
        "value": "0.375 ft³",
        "note": "72 bags"
      },
      {
        "label": "60 lb",
        "value": "0.45 ft³",
        "note": "60 bags"
      },
      {
        "label": "80 lb",
        "value": "0.60 ft³",
        "note": "45 bags"
      },
      {
        "label": "90 lb",
        "value": "0.675 ft³",
        "note": "40 bags"
      }
    ],
    "context": "Bagged mix makes sense up to about half a yard — beyond that, you're mixing 20+ bags by hand and paying a premium per yard. At 2026 prices (~$6–8 per 80-lb bag), a yard of bagged concrete runs $270–360 versus $150–190 for ready-mix delivered, before the short-load fee. The crossover is roughly 1–1.5 yards: below that bags win on convenience, above it call the plant.",
    "methodology": "Yields are the manufacturer-published values for standard 4,000-psi bagged mixes (Quikrete/Sakrete class). Ready-mix pricing reflects 2026 US national average range of $150–190 per cubic yard before delivery and short-load fees.",
    "dateModified": "2026-10-01",
    "relatedCalculators": [
      {
        "label": "Concrete Cost Calculator",
        "to": "/concrete-cost-calculator"
      },
      {
        "label": "Concrete Slab Cost Calculator",
        "to": "/concrete-slab-cost-calculator"
      },
      {
        "label": "Concrete Slab Material Calculator",
        "to": "/concrete-slab-material-calculator"
      }
    ],
    "relatedReading": [
      {
        "label": "How to calculate cubic yards",
        "to": "/answers/how-to-calculate-concrete-yards"
      }
    ]
  }
}